Host: Louis Fouejieu and Seth Evans
Original Story:
As an EQRS program manager, in order to start preview period, I want reports to be in production environment.
Acceptance criteria
- QIP Reports run in production
- Able to view reports in Prod
- The two new measures (PPPW & MedRec) are viewable in UI via Prod env
- Target is to receive final Preview Period data on October 28 under assumption that preview period starts on 11/8
- Added to 16.2 sprint
**NOTE - Need to edit tasks below to align with CI's needs**
Revised Story:
As a Facility Manager/Program Manager of the clinic, I want reports(PLR, PSR, PSSR) to be available and accessible in a production environment so that EQRS Program Manager can validate the accuracy of the data before the preview period is started.
Acceptance criteria
- Verify that QIP Reports (PLR, PSR, PSSR) are available and accessible in production by EQRS team members on 10/28
- Verify that QIP Reports (PLR, PSR, PSSR) are not available for the end-users (FM/PMC) until 11/18
- Verify that the two new measures (PPPW & MedRec) are viewable in UI via Prod env for the 3 reports (PLR, PSR, PSSR)
- Verify that QIP Reports (PLR, PSR, PSSR) can be downloaded
- Verify that the two new measures (PPPW & MedRec) are viewable on the downloaded copy for the 3 reports (PLR, PSR, PSSR)
**NOTE - Need to edit tasks below to align with CI's needs**
- Target is to receive final Preview Period data on October 28 under assumption that preview period starts on 11/18
- Added to 16.2 sprint