- Created by Phuong Dam on Mar 05, 2021
You are viewing an old version of this page. View the current version.
Compare with Current View Page History
Version 1 Next »
Date
Attendees
Name | |
---|---|
Ahmar Wazir | x |
Lisa Rees | x |
Curt Phillips | x |
Betina Fletcher | |
Adrienne Ray | x |
Kelly Llewellyn | x |
Heather Moore | x |
Kathleen Prewitt | x |
Chris Brown | x |
Vladimir Ladik | x |
Teresa Edmunds | x |
Nathan Muzos | x |
Leah Skien | |
Jason Bullock | x |
Hari Krishna | x |
Deb Wilson | x |
Karen Wheeler | x |
June Tran | x |
Cheri Jerger | x |
Jennifer Bailey | x |
Aaron Thompson | x |
Karena S | x |
Pandu Mudda | x |
Revathy Ramakrishna | x |
Agenda
Items | Who | Topics |
---|---|---|
Announcements | Ahmar/Curt |
|
Discuss Vlad's email regarding Phase 1 & 2 concerns | Vlad/Lisa/Ahmar | 11297 - Medicare Enrollment Status must be Medicare Coverage when Medicare Claim Number is populated.
11520 - Admit Reason of _{0} was replaced by the system with _{1} for the submitted Admit/Discharge.
11521 - Admit Reason can not be updated to _{0} because the current Admit Reason is _{1}.
13492 - Medicare Enrollment Effective Date of _{0} already exists in the system for Medicare Enrollment Status.
13559 - Admission Records created prior to _{0} cannot be modified via batch. Changes to the Admission Data were not processed. Please use the SUI to make any necessary updates.
13561 - Treatment Information on records created prior to _{0} cannot be modified via batch. Changes to the Treatment Information were not processed. Please use the SUI to make any necessary updates.
|
Warnings |
| |
Updates on phase 1 testing |
| |
EDI homework updates | Lisa/Curt |
|
PER and PRR reports | Nathan |
|
Data clean-up effort once codes are turned on |
| |
Next meeting on |
EDSM Validation Codes - Implementation Timeline
Date | Milestone (M) / Task (T) | Description | Phase | Status |
---|---|---|---|---|
2/28/2021 | M | Code deployed to pre-prod for testing. | 1 | Complete |
3/1/2021 - 3/12/2021 | T | EDIs performs integration testing. | 1 | In Progress |
3/12/2021 | M | EDIs sign-off on integration testing. | 1 | - |
3/13/2021 - 3/15/2021 | T | ADO prepares for coding deployment. | 1 | - |
3/15/2021 | M | Production deployment. | 1 | In Progress |
3/31/2021 | M | Prod-Preview environment contains refreshed prod data | 2 | In Progress |
2/24/2021 - 3/10/2021 | T | Review of phase 2 codes and finalize list of codes. | 2 | In Progress |
3/11/2021 - 4/9/2021 | T | ADO perform coding updates and regression testing. | 2 | - |
4/9/2021 | M | Code deployed to pre-prod for testing. | 2 | - |
4/9/2021 - 5/6/2021 | T | EDIs performs integration testing. | 2 | - |
5/6/2021 | M | EDIs sign off-on integration testing. | 2 | - |
5/7/2021 - 5/10/2021 | T | ADO prepares for coding deployment. | 2 | - |
5/11/2021 | M | Production deployment. | 2 | - |
3/10/2021 - 3/17/2021 | T | Review of phase 3 codes and finalize list of codes. | 3 | Under EDI Review |
3/31/2021 - 4/28/2021 | T | ADO perform coding updates and regression testing. | 3 | - |
4/28/2021 | M | Code deployed to pre-prod for testing. | 3 | - |
4/28/2021 - 5/27/2021 | T | EDIs performs integration testing. | 3 | - |
5/27/2021 | M | EDIs sign-off on integration testing. | 3 | - |
5/28/2021 - 5/31/2021 | T | ADO prepares for coding deployment. | 3 | - |
6/1/2021 | M | Production deployment. | 3 | - |
6/1/2021 | M | All phases complete. Production implementation. | 1-3 | In Progress |
6/30/2021 | M | Data ready to be used for measure and scoring calculations. | 1-3 | - |
Action Item:
- Follow up with Davita to see why they are not able to receive feedback file. Phuong Dam