Data Submission (Errors & Warnings) Implementation Timeline


DateMilestone (M) / Task (T)DescriptionPhaseStatus
2/28/2021MCode deployed to pre-prod for testing.1Complete
3/15/2021 - 3/24/2021TEDIs perform integration testing.1Complete

3/24/2021

MEDIs sign-off on integration testing.1Complete

3/24/2021 - 3/25/2021

TADO prepares for coding deployment.1Complete

3/25/2021

MProduction deployment.1Complete
3/31/2021MProd-Preview environment contains refreshed prod data 2Complete
2/24/2021 - 3/10/2021 TReview of phase 2 codes and finalize list of codes.  Complete
3/11/2021 - 4/30/2021TADO perform coding updates and regression testing - Phase 2 (Patient Codes) 2Complete

4/30/2021

MProd-Preview environment data refresh.2Complete

5/3/2021

MRemaining Phase 2 (Patient Codes) deployed to pre-prod for testing.2Complete

5/4/2021 - 6/1/2021

T

EDIs performs integration testing - Phase 2 (Patient Codes) 
Starting 5/4 - EDIs submit prod file in prod environment and PP2-3.  This should be the SAME file for both environments.  Review discrepancies between the feedback files and validate codes.

2Complete

6/2/2021

MEDIs sign off-on integration testing - Phase 2 (Patient Codes) 2Complete

6/2/2021 - 6/4/2021

TADO prepares for coding deployment - Phase 2 (Patient Codes) 2Complete

6/3/2021

MProduction deployment - Phase 2 (Patient Codes) 2Complete
6/4/2021MPhase 2 (Patient Codes) live in production.2Complete
3/10/2021 - 3/17/2021TReview of phase 3 codes and finalize list of codes.  3Complete
5/12/2021 - 06/08/2021TADO perform coding updates and regression testing - Phase 3 Clinical Codes/27283Complete

6/4/2021

MProd-Preview environment data refresh.
Complete
6/4/2021 - 6/6/2021T

EDIs SHOULD NOT submit any PATIENT files during this time period in production (to ensure same patients are in PP2-3).

3Complete
6/7/2021T

EDIs to drop file into PP2-3 to establish a baseline.

3Complete

6/8/2021

MCode deployed to pre-prod for testing - Phase 3 (Clinical Codes/2728).
Reopening September 2020 to March 2021 Clinical months for submission.
3Complete

6/9/2021 - 7/6/2021

TEDIs performs integration testing.

Starting 6/9 - Re-drop same file from 6/7/2021 into PP2-3.  Review feedback files from PP2-3 and validate codes.

3Complete

7/6/2021

MEDIs sign-off on integration testing - Phase 3 (Clinical Codes/2728).3

Complete

7/7/2021 - 7/11/2021

TADO prepares for coding deployment - Phase 3 (Clinical Codes/2728).3Complete
7/12/2021MPhase 3 (Clinical Codes/2728) live in production.3Complete

7/12/2021

MEDSM Implementation Complete (Phase 1 - 3).n/aComplete

7/12/2021 - 9/15/2021




T

Resubmission of Clinical Data Files (September to December). 

Open July 12, 2021 at 5 a.m. Pacific (8 a.m. Eastern) and close September 15, 2021 at 11:59 p.m. Pacific Daylight Time

9/15/2021 is the official closure date for the clinical months of September, October, November, and December 2020.

CMS highly recommends completing large data submissions prior to the official clinical closure date.


n/a

Complete


9/15/2021


M

Data fully submitted and ready for measure and scoring calculations.



n/aComplete
09/20/2021 - 02/28/2022T

Submit January-September 2021 EQRS Clinical Data, ICH CAHPS Attestations, and Clinical Depression Screening and Follow-Up Plan reporting in EQRS. Additionally, all subsequent months in 2021 will open for data submission on the first day of each month (i.e., October opens October 1; November opens November 1; and December opens December 1). 

n/a
02/28/2022MThe clinical closure date for all months in 2021 is February 28, 2022 at 11:59 PM PT.n/a

Data Submission (Errors & Warnings) Milestone Dates - By Phase


Phase No.

File Type

Code Bucket Name

Codes

ADO Completion Date

LDO Testing Start Date

Testing Completion Date

Production Date

1

Patient

Admit Reasons

11221, 11222, 11223, 11224, 11225

2/24/2021

3/1/2021

3/24/2021

3/25/2021

2

Patient

Patient Codes


5/3/2021

5/4/2021

6/1/2021

6/7/2021

3

Clinical

Clinical Codes


6/8/2021

6/9/2021

7/6/2021

7/12/2021

3

2728

2728 Codes


6/8/2021

6/9/2021

7/6/2021

7/12/2021



EQRS EDI Meeting Minutes



EQRS Error & Warning (Validation Code) Implementation



EQRS Documentations

No files shared here yet.

EQRS EDI Issues

As of March 3, 2021


Status

LDO Impact

Task(s)

Projected Completion Date

Percent Complete

Change

Error Validation Codes

  • Turning error codes back on for data validations.
  • Phase 1 (Admit Reason Codes) to be in production by 3/15/2021.
  • Phase 2 (Patient Codes) to be in production by xx
  • Phase 3 (Clinical and 2728 Codes) to be in production by.
  • Implementation Completion Date = 6/1/2021.

6/1/2021

10%

Reporting to support Form 2744

  • PER and PRR reporting not available to perform research necessary to complete Form 2744
0/00/2021

0%

Reporting:  Clinical Compliance, UNOS, Error Trends

  • Clinical Compliance Report to support Clinical Submission data.  Weekly. 

  • Clinical Compliance Report to support Clinical Submission data.  Monthly (after clinical months have closed).  

  • UNOS Report to support patients placement on to transplant waiting list.

  • Error Trends Report to support identifying top 10 most frequent errors across EDI submitters.
TBD

50%

Turning Clinical Submission back on

  • Turning error codes back on for data validations.

6/1/2021

10%