Date | Milestone (M) / Task (T) | Description | Phase | Status |
---|---|---|---|---|
2/28/2021 | M | Code deployed to pre-prod for testing. | 1 | Complete |
3/15/2021 - 3/24/2021 | T | EDIs perform integration testing. | 1 | Complete |
3/24/2021 | M | EDIs sign-off on integration testing. | 1 | Complete |
3/24/2021 - 3/25/2021 | T | ADO prepares for coding deployment. | 1 | Complete |
3/25/2021 | M | Production deployment. | 1 | Complete |
3/31/2021 | M | Prod-Preview environment contains refreshed prod data | 2 | Complete |
2/24/2021 - 3/10/2021 | T | Review of phase 2 codes and finalize list of codes. | 2 | Complete |
3/11/2021 - 4/30/2021 | T | ADO perform coding updates and regression testing - Phase 2 (Patient Codes) | 2 | Complete |
4/30/2021 | M | Prod-Preview environment data refresh. | 2 | Complete |
5/3/2021 | M | Remaining Phase 2 (Patient Codes) deployed to pre-prod for testing. | 2 | Complete |
5/4/2021 - 6/1/2021 | T | EDIs performs integration testing - Phase 2 (Patient Codes) | 2 | Complete |
6/2/2021 | M | EDIs sign off-on integration testing - Phase 2 (Patient Codes) | 2 | Complete |
6/2/2021 - 6/4/2021 | T | ADO prepares for coding deployment - Phase 2 (Patient Codes) | 2 | Complete |
6/3/2021 | M | Production deployment - Phase 2 (Patient Codes) | 2 | Complete |
6/4/2021 | M | Phase 2 (Patient Codes) live in production. | 2 | Complete |
3/10/2021 - 3/17/2021 | T | Review of phase 3 codes and finalize list of codes. | 3 | Complete |
5/12/2021 - 06/08/2021 | T | ADO perform coding updates and regression testing - Phase 3 Clinical Codes/2728 | 3 | In Progress |
6/4/2021 | M | Prod-Preview environment data refresh. | Complete | |
6/4/2021 - 6/6/2021 | T | EDIs SHOULD NOT submit any PATIENT files during this time period in production (to ensure same patients are in PP2-3). | 3 | Complete |
6/7/2021 | T | EDIs to drop file into PP2-3 to establish a baseline. | 3 | Complete |
6/8/2021 | M | Code deployed to pre-prod for testing - Phase 3 (Clinical Codes/2728). Reopening September 2020 to March 2021 Clinical months for submission. | 3 | Complete |
6/9/2021 - 7/6/2021 | T | EDIs performs integration testing. Starting 6/9 - Re-drop same file from 6/7/2021 into PP2-3. Review feedback files from PP2-3 and validate codes. | 3 | In Progress |
7/6/2021 | M | EDIs sign-off on integration testing - Phase 3 (Clinical Codes/2728). | 3 | - |
7/7/2021 - 7/11/2021 | T | ADO prepares for coding deployment - Phase 3 (Clinical Codes/2728). | 3 | - |
7/12/2021 | M | Phase 3 (Clinical Codes/2728) live in production. | 3 | - |
7/12/2021 | M | EDSM Implementation Complete (Phase 1 - 3). | n/a | In Progress |
07/12/2021 - 08/31/2021 | T |
8/31/2021 is the official closure date for the clinical months of September, October, November and December 2020. Resubmission of Clinical Data Files (September to December). Data entry for UI users. | n/a | Description revised and date range extended 06/18/2021 |
8/23/2021 - 8/30/2021 | M |
CMS highly recommends to do large data submissions ahead of the official clinical closure date. We recommend that you follow this timeframe. Data Cleanup (patient merges, duplicates, fallout from phases). | Description revised 06/18/2021 | |
8/31/2021 | M |
Data fully submitted by EDIs and ready for upstream consumption. | n/a | Description revised 06/18/2021 |
Data Submission (Errors & Warnings) Milestone Dates - By Phase
Phase No. | File Type | Code Bucket Name | Codes | ADO Completion Date | LDO Testing Start Date | Testing Completion Date | Production Date |
---|---|---|---|---|---|---|---|
1 | Patient | 11221, 11222, 11223, 11224, 11225 | 2/24/2021 | 3/1/2021 | 3/24/2021 | 3/25/2021 | |
2 | Patient | 5/3/2021 | 5/4/2021 | 6/1/2021 | 6/7/2021 | ||
3 | Clinical | 6/8/2021 | 6/9/2021 | 7/6/2021 | 7/12/2021 | ||
3 | 2728 | 6/8/2021 | 6/9/2021 | 7/6/2021 | 7/12/2021 |