CMS has redesigned the Documentation Repository on the EQRS Communications Hub. This change simplifies your file searches and makes it easier for you to find the information you need. The XSD table clearly indicates which files are in Production and Prod Preview. The Supporting Documents table includes files that support the XSD files, giving you more context and detail. The Sample table includes XML files. The Feedback Files table contains formats for the EDSM submission file feedback. |
Image Added
Section |
---|
Anchor |
---|
EQRSEDIIssues | EQRSEDIIssues | EQRS EDI IssuesAs of March 3, 2021
Image Removed
Image Removed
Status | LDO Impact | Technical Issue(s) | Projected Completion Date | Percent Complete | Change |
---|
Image Removed
| Error Validation Codes | - Turning error codes back on for data validations.
- Phase 1 (Admit Reason Codes) to be in production by 3/15/2021.
- Phase 2 (Patient Codes) to be in production by xx
- Phase 3 (Clinical and 2728 Codes) to be in production by.
- Implementation Completion Date = 6/1/2021.
| 6/1/2021 | 10% | Image Removed
|
Image Removed
| | - PER and PRR reporting not available to perform research necessary to complete Form 2744
| 0/00/2021 | 0% | Image Removed
|
Image Removed
| Reporting: Clinical Compliance, UNOS, Error Trends | -
Clinical Compliance Report to support Clinical Submission data. Weekly. -
Clinical Compliance Report to support Clinical Submission data. Monthly (after clinical months have closed). -
UNOS Report to support patients placement on to transplant waiting list. - Error Trends Report to support identifying top 10 most frequent errors across EDI submitters.
| TBD | 50% | Image Removed
|
Image Removed
| Turning Clinical Submission back on | | 6/1/2021 | 10% | Image Removed
|
Image Removed
| -
Bullet point -
Bullet point
| 0/00/2021 | 0% | Image Removed
| Data Submission (Errors & Warnings) Implementation Timeline
Excerpt |
---|
Date | Milestone (M) / Task (T) | Description | Phase | Status |
---|
2/28/2021 | M | Code deployed to pre-prod for testing. | 1 | Complete |
3/1/2021 - 3/12/2021 | T | EDIs performs integration testing. | 1 | In Progress |
3/12/2021 | M | EDIs sign-off on integration testing. | 1 | - |
3/13/2021 - 3/15/2021 | T | ADO prepares for coding deployment. | 1 | - |
3/15/2021 | M | Production deployment. | 1 | In Progress |
3/31/2021 | M | Prod-Preview environment contains refreshed prod data | 2 | In Progress |
2/24/2021 - 3/10/2021 | T | Review of phase 2 codes and finalize list of codes. | 2 | In Progress |
3/11/2021 - 4/9/2021 | T | ADO perform coding updates and regression testing. | 2 | - |
4/9/2021 | M | Code deployed to pre-prod for testing. | 2 | - |
4/9/2021 - 5/6/2021 | T | EDIs performs integration testing. | 2 | - |
5/6/2021 | M | EDIs sign off-on integration testing. | 2 | - |
5/7/2021 - 5/10/2021 | T | ADO prepares for coding deployment. | 2 | - |
5/11/2021 | M | Production deployment. | 2 | - |
3/10/2021 - 3/17/2021 | T | Review of phase 3 codes and finalize list of codes. | 3 | Under EDI Review |
3/31/2021 - 4/28/2021 | T | ADO perform coding updates and regression testing. | 3 | - |
4/28/2021 | M | Code deployed to pre-prod for testing. | 3 | - |
4/28/2021 - 5/27/2021 | T | EDIs performs integration testing. | 3 | - |
5/27/2021 | M | EDIs sign-off on integration testing. | 3 | - |
5/28/2021 - 5/31/2021 | T | ADO prepares for coding deployment. | 3 | - |
6/1/2021 | M | Production deployment. | 3 | - |
6/1/2021 | M | All phases complete. Production implementation. | 1-3 | In Progress |
6/30/2021 | M | Data ready to be used for measure and scoring calculations. | 1-3 | - |
Anchor |
---|
EQRSEDIMeetingMinutes | EQRSEDIMeetingMinutes | EQRS EDI Meeting Minutes Content Report Table |
---|
spaces | ELDF |
---|
labels | eqrs-working-group-meeting |
---|
|
Anchor |
---|
EQRSErrorsandWarnings | EQRSErrorsandWarnings | EQRS Documentations Attachments |
---|
patterns | *xlsx, *.pdf