DateMilestone (M) / Task (T)DescriptionPhaseStatus
2/28/2021MCode deployed to pre-prod for testing.1Complete
3/15/2021 - 3/24/2021TEDIs perform integration testing.1Complete

3/24/2021

MEDIs sign-off on integration testing.1Complete

3/24/2021 - 3/25/2021

TADO prepares for coding deployment.1Complete

3/25/2021

MProduction deployment.1Complete
3/31/2021MProd-Preview environment contains refreshed prod data 2Complete
2/24/2021 - 3/10/2021 TReview of phase 2 codes and finalize list of codes.  Complete
3/11/2021 - 4/30/2021TADO perform coding updates and regression testing - Phase 2 (Patient Codes) 2Complete

4/30/2021

MProd-Preview environment data refresh.2Complete

5/3/2021

MRemaining Phase 2 (Patient Codes) deployed to pre-prod for testing.2Complete

5/4/2021 - 6/1/2021

T

EDIs performs integration testing - Phase 2 (Patient Codes) 
Starting 5/4 - EDIs submit prod file in prod environment and PP2-3.  This should be the SAME file for both environments.  Review discrepancies between the feedback files and validate codes.

2Complete

6/2/2021

MEDIs sign off-on integration testing - Phase 2 (Patient Codes) 2Complete

6/2/2021 - 6/4/2021

TADO prepares for coding deployment - Phase 2 (Patient Codes) 2Complete

6/3/2021

MProduction deployment - Phase 2 (Patient Codes) 2Complete
6/4/2021MPhase 2 (Patient Codes) live in production.2Complete
3/10/2021 - 3/17/2021TReview of phase 3 codes and finalize list of codes.  3Complete
5/12/2021 - 06/08/2021TADO perform coding updates and regression testing - Phase 3 Clinical Codes/27283In Progress

6/4/2021

MProd-Preview environment data refresh.
Complete
6/4/2021 - 6/6/2021T

EDIs SHOULD NOT submit any PATIENT files during this time period in production (to ensure same patients are in PP2-3).

3Complete
6/7/2021T

EDIs to drop file into PP2-3 to establish a baseline.

3Complete

6/8/2021

MCode deployed to pre-prod for testing - Phase 3 (Clinical Codes/2728).
Reopening September 2020 to March 2021 Clinical months for submission.
3Complete

6/9/2021 - 7/6/2021

TEDIs performs integration testing.

Starting 6/9 - Re-drop same file from 6/7/2021 into PP2-3.  Review feedback files from PP2-3 and validate codes.

3In Progress

7/6/2021

MEDIs sign-off on integration testing - Phase 3 (Clinical Codes/2728).3-

7/7/2021 - 7/11/2021

TADO prepares for coding deployment - Phase 3 (Clinical Codes/2728).3-
7/12/2021MPhase 3 (Clinical Codes/2728) live in production.3-

7/12/2021

MEDSM Implementation Complete (Phase 1 - 3).n/aIn Progress

7/12/2021 - 8/22/2021

07/12/2021 - 08/31/2021

T

Resubmission of Clinical Data Files (September to December). 
Expectation:  EDIs should be reviewing feedback files and performing any data cleanup immediately afterwards.

Data entry for UI users.

8/31/2021 is the official closure date for the clinical months of September, October, November and December 2020.

Resubmission of Clinical Data Files (September to December). 
Expectation:  EDIs should be reviewing feedback files and performing any data cleanup immediately afterwards.

Data entry for UI users.

n/a

Description revised and date range extended 06/18/2021


8/23/2021 - 8/30/2021M

Data Cleanup (patient merges, duplicates, fallout from phases).

CMS highly recommends to do large data submissions ahead of the official clinical closure date. We recommend that you follow this timeframe.

Data Cleanup (patient merges, duplicates, fallout from phases).


Description revised 06/18/2021

8/31/2021

M

Data ready to be used for measure and scoring calculations.

Data fully submitted by EDIs and ready for upstream consumption.

n/a-Description revised 06/18/2021



Data Submission (Errors & Warnings) Milestone Dates - By Phase

...