*This clinic outcomes page will be posted in a confluence space available to all Federal and contractor employees in the CCSQ Community


.


Submit a list of features in the chat and work together to estimate the components of Cost Of Delay and WSJF

WSJF Worksheet:

Fibonacci Sequence: 1,2,3,5,8,13,20

Work together to estimate the components of the Cost of Delay


Feature Name   BV  TC RR/OE  COD Job Size WSJF Score
1Patient Contact Utility (PCU) – Reports2020206087.5
2UI - Data intake of ECE functionality13852683.25
3PY 2024 Implementation of changes to existing measures20883657.2
4Exploration Enabler: Communication with the transplant centers2020206087.5
















Responsibilities:

Job Size: ADO, after feature refinement

User-Business Value: SMT, decides during PI planning

Time Criticality: Feature Owner, Product Managers, and Solution Architects

RR/OE: Product Managers, ADO Product Owners


Recommend beginning WSJF Evaluation during the Analyzing phase on the program KanBan