*This clinic outcomes page will be posted in a confluence space available to all Federal and contractor employees in the CCSQ Community
.
Submit a list of features in the chat and work together to estimate the components of Cost Of Delay and WSJF
WSJF Worksheet:
Fibonacci Sequence: 1,2,3,5,8,13,20
EQRS Program: Curtis Phillips seema sreenivas Aaron Thompson Ahmar Wazir Justyna Sardin Michael Kennedy Yvette Brown Scott Laughlin
Work together to estimate the components of the Cost of Delay
Feature Name | BV | TC | RR/OE | COD | Job Size | WSJF Score | |
---|---|---|---|---|---|---|---|
1 | Patient Contact Utility (PCU) – Reports | 20 | 20 | 20 | 60 | 8 | 7.5 |
2 | UI - Data intake of ECE functionality | 13 | 8 | 5 | 26 | 8 | 3.25 |
3 | PY 2024 Implementation of changes to existing measures | 20 | 8 | 8 | 36 | 5 | 7.2 |
4 | Exploration Enabler: Communication with the transplant centers | 20 | 20 | 20 | 60 | 8 | 7.5 |
Responsibilities:
Job Size: ADO, after feature refinement
User-Business Value: SMT, decides during PI planning
Time Criticality: Feature Owner, Product Managers, and Solution Architects
RR/OE: Product Managers, ADO Product Owners
Recommend beginning WSJF Evaluation during the Analyzing phase on the program KanBan