HCD Team



Iteration Planning

Foundation
  • Timebox: 2-4hrs/2 weeks iteration
  • Purpose: The team defines and commits to what will be built in the next Iteration
  • Attendees: PO, SM, Agile Team, and invited stakeholders
  • Facilitator: SM or PO
  • Preparation:
    • Team capacity and velocity are established
    • Team PI Objectives and Features
    • Candidate's stories for the iteration are READY and prioritized
Meeting's flow
  1. Establish the Team’s capacity and velocity
  2. Revisit all the READY stories/enablers for the Iteration
  3. Discuss how to complete each story/enabler
  4. Load stories into the Iteration until capacity is reached
  5. The team commits to the iteration goals
Recommended practices
  •  Invited Development stakeholders are present
  •  Team capacity and velocity/load are revisited if necessary
  •  DoR and DoD for the sprint are revisited if necessary
  •  Each story/enabler is revisited (description, AC, size, ...) and passes the DoR
  •  Team capacity allocation is established (load allocated for maintenance, refactors, tech debt, or any relevant work item type)
  •  Sub-tasks are created to highlight how to complete a story/enabler when necessary
  •  Stories & enablers planned for the upcoming Iteration respect the team's velocity
  •  Iteration's goals are defined
  •  The team commits to achieving iteration goals
  •  Iteration is started at the end of the meeting
Notes from HCD Observation



Daily Stand-up

Foundation 
  • Timebox: 15 mins daily
  • Purpose: Daily checkpoint to synchronize and collaborate on achieving the Iteration Goals.
  • Attendees: Agile Team members, SM, PO
  • Facilitator: SM
  • Preparation: Updated work management tool or team board
Meeting's flow

Each Agile team member answer the questions:

  1. What did I do yesterday to advance the Iteration Goals?
  2. What will I do today to advance the Iteration Goals?
  3. Are there any impediments that will prevent the team from meeting the Iteration Goals?
Recommended practices
  •  Team member collaborates and synchronizes their work around the board 
  •  Alignment across the work until the next business day is created
  •  Risks/impediments blocking the team are surfaced
  •  Potential impacts on cross-depending teams or work items are discussed
  •  Stories/enablers are moved to "Done" when they pass the DoD 
  •  Sprint Burndown is shown to assess the progress toward the completion of the sprint goal & commitment
  •  16th minutes topics or follow up actions are agreed
Notes from HCD Observations

DSU on  

  • Attendees: Rob Fay, Meaghan Hudak, Chelsea Brigg, Howard Montgomery, Amy Castellani. 
  • Status report from the team 
  • Several times Scrum Master was interrupted not being empowered for SM to play the role of Scrum Master
  • Scrum Master shared (16min) parking lot for further discussions
  • Great conversations about community and HCD and how they can plug into other areas. Artifacts and knowledge sharing, personas development
  • The parking lot turned into a sharing knowledge session where Chelsea shared the functionality of a new tool with HCD team 
  • No discussion about sprint goals
  • Metrics were not shared, burn down or progress toward meeting the sprint commitment
  • Dependencies or blockers seemed a bit unclear. 
  • The waiting column on kanban board doesn't appear to have WIP limits making it difficult to assess blockers or impediments. 




...